Recently, the reporter came to the site of Guangxi Qifeng New Materials Co., Ltd. with an annual output of 200,000 tons of special paper project located in the city's industrial park Guangyugui Park to see that the main structure of the project has been completed, and the peripheral decoration and equipment installation of the plant have entered the final stage. Zhang Weijin, manager of the power Department of Guangxi Qifeng New Materials Co., LTD., told reporters that the city's rich forestry resources, complete upstream and downstream industry chains, convenient export of products to Southeast Asia and good business environment, attracted them to settle down in Guigang development.
Zhang Weijin, manager of the Power Department of Guangxi Qifeng New Materials Co., LTD. : Since the signing of our project, the park has given us strong support in all aspects, especially in terms of electricity, gas and water, and is actively coordinating.
Guigang high-tech Zone housing construction and municipal Administration director, Qifeng new materials project service commissioner Huang Qike: mainly based in the park this party group to implement the service commissioner system, each enterprise arrangements for a leader to track the service enterprise, the main coordination of the enterprise's water and electricity and construction and other processes. For example, in the process of our first-line research, Qifeng new materials project found that there was no way to solve industrial water, the enterprise entrance and exit were not opened, and the enterprise steam was not perfect. We studied in the first-line to help solve these problems and ensure that the enterprise could smoothly put into operation.
At present, Guangxi Qifeng New Materials Co., Ltd. annual output of 200,000 tons of special paper project progress steadily, project owners and construction units are grasping the weather conditions conducive to construction, strictly grasp the safety of production, environmental protection, engineering quality and other premises, increase human, financial, material investment, scientific arrangement of construction, do everything possible to speed up the construction of the project.
Zhang Weijin, Manager of Power Department of Guangxi Qifeng New Materials Co., LTD. : The current project is in the installation stage, the indoor equipment is being installed at the final stage, and the outdoor pipe network is being laid. We plan to enter the production stage in June.